New Hospital Programme annual report sets baseline for delayed hospital building pipeline
The government’s first annual report on the New Hospital Programme provides new detail on scheme status, funding and delivery oversight following the 2025 reset. It confirms seven schemes are open to patients, nine hospitals are in construction and £1.83 billion has been provided to trusts since 2021 to 2022. It also shows that many schemes remain in business case development, with some major rebuilds not due to start main construction until the 2030s.
The government has published its first annual report on the New Hospital Programme (NHP), covering progress during the 2025 to 2026 financial year.
Released today (8 July) The report follows the January 2025 reset of the programme. That reset replaced the previous commitment to deliver 40 new hospitals by 2030 with a longer wave-based timetable, after ministers concluded that the original programme lacked sufficient funding certainty beyond 2025.
The document describes the NHP as a 46-scheme capital programme. It says the government has allocated £9.6 billion over the current Spending Review period, with future investment expected to rise to up to £15 billion for each five-year delivery wave from 2030.
The report also gives Parliament a baseline against which future progress can be assessed. It does not provide revised opening dates for every scheme, and several later-wave projects remain at early stages of development.
Seven schemes open to patients
The report says seven NHP schemes are now open to patients: Royal Liverpool Hospital, Dyson Cancer Centre in Bath, Midland Metropolitan University Hospital, Brighton 3Ts, Northern Centre for Cancer Care, Greater Manchester Major Trauma Hospital and the Care Environment Development and Re-provision Programme.
The Brighton 3Ts scheme is only partly complete. The Louisa Martindale Building is open, but the Sussex Cancer Centre remains under construction. The programme will count the full scheme as complete once the Sussex Cancer Centre opens and ancillary works are finished.
The report also says nine hospitals are in construction. During 2025 to 2026, seven main scheme business cases were approved, including four strategic outline cases and three full business cases. A further 13 are in active development.
These figures show movement across the programme, but also indicate how much of the pipeline remains subject to further approval before main construction can begin.
RAAC schemes remain a priority
The seven hospital schemes affected by reinforced autoclaved aerated concrete (RAAC) remain a primary focus for the programme.
The annual report says the RAAC replacement schemes have been assessed as safe to remain open beyond 2030 if appropriate mitigations remain in place. It also states that they will remain a primary focus in 2026 to 2027.
Progress varies across the seven schemes. Hinchingbrooke Hospital, James Paget Hospital, Leighton Hospital and Queen Elizabeth Hospital King’s Lynn moved from strategic outline case development into outline business case development during the year. Airedale General Hospital and Frimley Park Hospital remained in strategic outline case assurance. West Suffolk Hospital remained in outline business case development.
The report therefore confirms continued prioritisation of RAAC replacement, while showing that several schemes remain some distance from full business case approval and construction.
Hospital 2.0 design products due in 2026
Hospital 2.0 – the standardised building blueprint being used throughout the NHP – remains central to the programme’s delivery model. The government says the approach will use standardised designs and planning assumptions to support more consistent hospital construction.
The annual report says the Hospital 2.0 design is “substantively complete”. A full-scale single bedroom prototype was tested in October 2025, and final design products are due in summer 2026.
The report says Hospital 2.0 will apply to all schemes from wave one onwards. This means the standardised design model will need to support a wide range of local schemes, including RAAC replacements, specialist facilities and large multi-site rebuilds.
The programme also appointed 10 construction firms to the Hospital 2.0 Alliance in March 2026. The government says this framework is intended to support shared standards, supply chain learning and the concurrent delivery of several schemes.
However, the report does not yet show whether this commercial model will reduce delays or cost growth once multiple large schemes move into construction.
Programme receives amber rating
The NHP received an amber delivery confidence rating from the National Infrastructure and Service Transformation Authority in March 2026.
The annual report says this rating indicates that successful delivery is feasible, while recognising the need for continued work on risk management, governance and programme capability. It also notes that more than 60 per cent of projects in the Government Major Projects Portfolio were rated amber in 2024 to 2025.
It identifies several sources of delivery pressure, including wider system reform, economic and geopolitical conditions, market capacity, clinical transformation, digital maturity and complex construction requirements.
These risks are relevant to both programme-level delivery and individual schemes. Several hospitals will require significant enabling works, land acquisition, decanting or infrastructure upgrades before construction can proceed.
Funding has reached all delivery waves, but later-wave progress is limited
The report says NHP funding was provided across all waves during 2025 to 2026.
Wave zero schemes received £227 million during the year, while wave one schemes received £250 million. Wave two received £44 million and wave three received £61 million. Since 2021 to 2022, the programme has provided £1.83 billion to trusts.
Most current funding remains concentrated in the earlier waves, where schemes are in construction or more advanced development. Funding for later waves is being used largely for preparatory work, including land purchases, enabling infrastructure and business case development.
Wave two schemes are scheduled to start main construction between 2030 and 2035. Wave three schemes are scheduled to start between 2035 and 2039. Funding in these waves therefore indicates continued scheme development, not imminent full construction.
The scheme-level annex shows a varied picture across the programme.
In wave zero, Dorset County Hospital, Oriel Eye Hospital and Royal Bournemouth Hospital remained in construction during the reporting period. St Ann’s Hospital completed construction in April 2026 and Alumhurst Road Children’s Mental Health Unit completed construction in May 2026, after the end of the financial year covered by the report.
In wave one, main construction started at Brighton 3Ts Sussex Cancer Centre, Derriford Emergency Care Hospital and Poole Hospital. Cambridge Cancer Research Hospital remained in full business case development.
Wave two and wave three schemes are at earlier stages. Kettering General Hospital began enabling works, Whipps Cross University Hospital opened a multi-storey car park, and land was purchased for Hampshire Hospitals and Royal Preston Hospital. Several schemes in waves two and three were recorded as having “limited activity”.
This pattern broadly reflects the reset timetable, which moved a number of schemes into later delivery windows.
Progress against the implementation plan
The annual report shows that the NHP has introduced more regular reporting, clearer scheme-stage information and additional programme oversight since the reset.
During 2025 to 2026, the programme strengthened its governance arrangements, clarified responsibilities between the Department of Health and Social Care and NHS England, and held nine programme board meetings. The report says the board’s role is to provide scrutiny, advice and decision-making to keep the programme aligned with its objectives.
The programme has also put several delivery mechanisms in place, including the Health Delivery Partnership, the Hospital 2.0 Alliance and the New Hospital Programme Academy.
These changes improve the information available on programme management and scheme progress. They do not, in themselves, demonstrate that later-wave schemes will proceed within the revised timetable or avoid cost pressures.
The report is therefore best read as an initial post-reset baseline. Future annual reports will need to show whether schemes are moving through business case approval and construction at the pace assumed in the implementation plan.